Hot Posts

6/recent/ticker-posts

TCN NOTIFIES OF PLANNED MAINTENANCE AT 330/132/33kV KATAMPE TRANSMISSION SUBSTATION

 


The Transmission Company of Nigeria (TCN) wishes to inform the public that its maintenance crew will carry out scheduled maintenance at the 330/132/33kV Katampe Transmission Substation on Saturday, November 28, 2026, from 8:00am to 6:00pm.

A press statement by the TCN maintenance exercise is to facilitate the reconnection of the jumpered conductors to the newly installed 330kV incomer line disconnector switch with earthing switch.

Consequently, Abuja Electricity Distribution Company (AEDC) will be unable to off-take electricity for onward distribution to customers in parts of Kubwa, Bwari, Deidei, Zuba, Kaduna Road, Dakwa, Sabon Wuse, parts of Gwarimpa, Dawaki and environs during the maintenance period.

TCN apologizes for any inconvenience this interruption will cause electricity customers in the affected areas.

Post a Comment

0 Comments